Traffic Engineering will Be Implemented Due to Sudirman Bicycle Crossing Bridge Construction

Jakarta Transportation Agency implemented traffic engineering on Jalan Jenderal Sudirman, between Mayapada Tower and Le Meridien due to Karet Sudirman Bicycle Crossing Bridge (JPS).    

We implement traffic engineering according to the phase of work

Jakarta Transportation Agency Head, Syafrin Liputo mentioned, his side will first dismantle Transjakarta Karet Sudirman pedestrian crossing (JPO) before building JPS.

This construction work takes about 6 months to finish, from April 1 to September 2021. It includes dismantling roofs, ramp, as well as installing steel lifts, steel stairs, JPS floors and steel platforms.

MRT Jakarta Receives Award from MURI as the Most Bicycle Facility Provider

"In order to support it, we implement traffic engineering according to the phase of work," he said, Wednesday (3/31).

During the construction, Transjakarta Karet JPO users will be directed to use pelican crossing.

"We urge road users to avoid these roads and can follow the prevailing traffic regulations, traffic signs, instruction from officers on the field, and prioritize safety on the road," he asserted.

For information, here is traffic engineering which implemented according to phase of work;

- JPO demolishing work on west and east sides of Jalan Jenderal Sudirman on April 2-31, 2021 at 22.00-04.00. Two lanes will be closed.

-West JPS girder installation work on June 24, 2021 at 22.00-04.00:

• Traffic flow from south (Semanggi) to north (Bundaran HI) will be diverted to Jalan K.H. Mas Mansyur - U-turn - Jalan Karet Pasar Baru Timur 5 - Jalan Jenderal Sudirman;

• Traffic flow from north (Bundaran HI) to south (Semanggi) normal

- JPS structure and architecture installation work on west, east, and middle sides (median) from May 1 to August 16, 2021 at 22.00-04.00. Two lanes will be closed.

- East JPS girder installation on July 8, 2021 at 22.00-04.00:

• Traffic flow from north (Bundaran HI) to south (Semanggi) will be diverted to Landmark - Jalan Galunggung - Jalan RM. Margono Djojohadikoesoemo - Jalan K.H. Mansyur - Jalan Prof. Dr. Satrio - U-turn - Jalan Jenderal Sudirman.

• Traffic flow from south (Semanggi) to North (Bundaran HI) normal.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1205 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1049 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye903 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye728 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye568 personDessy Suciati